How to Compare Contractor Quotes in Nigeria (Free Sheet)

· · 6 min read
How to Compare Contractor Quotes in Nigeria (Free Sheet)

You've asked three contractors to price your house, and the quotes are in: ₦41.3 million, ₦33.6 million and ₦41.6 million. It's tempting to take the ₦33.6 million and save ₦7 million. But a quote that low is often missing work, under-priced in a way that comes back as variations, or from a contractor who will struggle to finish.

Is this quote fair?

Upload a contractor's quote, even a photo of a handwritten one, and see each line compared with current market rates.

Check a quote →

Here is how to compare quotes properly. It takes an evening with a spreadsheet, and it's the most valuable evening of your whole project.

Step 1: Get Your Own Estimate First

You can't judge a quote without a yardstick. Before the quotes arrive, get your own estimate of what the building should cost, section by section. Our free Building Cost Estimator gives you a priced breakdown in minutes, or use a QS. In our example, the estimate is ₦40.8 million.

Step 2: Make the Quotes Comparable

Quotes come in every format: a one-page lump sum, a BoQ, a WhatsApp photo of a handwritten page. To compare them, you need the same sections in each. The easiest way is to send every contractor the same scope and the same BoQ (our Invitation to Tender template helps). Otherwise, regroup each quote into the same sections yourself:

SectionYour estimateABC
Preliminaries₦1.8M₦2.5M₦1.2M₦1.9M
Substructure₦6.2M₦6.0M₦4.1M₦6.4M
Frame & blockwork₦9.8M₦10.2M₦8.9M₦9.6M
Roofing₦5.4M₦5.1M₦5.0M₦5.8M
Doors & windows₦4.3M₦4.0M₦3.9M₦4.5M
Finishes₦8.1M₦8.6M₦6.2M₦8.3M
Electrical & plumbing₦5.2M₦4.9M₦4.3M₦5.1M
Total₦40.8M₦41.3M₦33.6M₦41.6M

Our comparison sheet works out how far each total is from your estimate. Here Contractor B is 17.6% below.

Step 3: Look Section by Section, Not at the Total

Contractor B isn't cheaper everywhere. Most sections are a little below the estimate, but two stand out: substructure (₦2.1M under) and finishes (₦1.9M under). That's where to ask questions:

  • Substructure far too low? Check the foundation depth and width, whether blockwork below DPC is filled solid, whether hardcore, anti-termite treatment and DPM are included. Our sample substructure takeoff lists every item a foundation quote should have.
  • Finishes far too low? Usually a cheaper tile, paint or ceiling than you expect, fewer coats, or wall tiling left out.
  • Preliminaries very low? Who pays for water, the site store, security and supervision? They'll be paid somewhere.

A low section is not automatically bad. The contractor may have a cheaper source. But you should know why before you sign. If the answer is "it's not included", add it back and compare again.

Step 4: Score More Than Price

A contractor who finishes on time at ₦41M is cheaper than one who abandons the job at ₦34M. Score each bidder on what actually predicts a good job:

CriterionWeightWhat to check
Price40%Lowest realistic price scores highest
Similar past projects20%Visit two finished buildings; call those clients
Programme and method15%A realistic week-by-week plan
Team on site15%Who is the supervisor? How often will they be there?
Documents10%CAC, tax, insurance, references

In our example, A scores 78, C 75 and B 56.5. B's price advantage doesn't survive its thin track record and team.

Step 5: Negotiate, Then Award in Writing

With the comparison in hand you can negotiate from facts: "Your preliminaries are ₦700,000 above our estimate; can you bring them closer?" When you've decided, award the job with a letter of award that fixes the sum, period, payment stages and retention.

One Quote? Check It Line by Line

If you only have one quote, the same principle applies: compare it with an estimate, section by section. Our Quote Checker reads a quote (even a photo of a handwritten one) and compares each line with current market rates. Contractors can make their own clear quotes with our Quotation template or the free Quotation Generator.

Red Flags in Any Quote

  • A single lump sum with no breakdown.
  • "Labour only" when you thought it was supply and fix.
  • No validity date, so prices can be changed when cement goes up.
  • A large advance (over 30–40%) before any work.
  • Items described vaguely ("roofing complete") with no sizes or specifications.

Questions to Ask Every Bidder

  • Is your price supply-and-fix or labour-only? Which materials do I buy?
  • Which items are excluded? (Plastering, electrical, plumbing, fence, external works and approvals are commonly left out.)
  • How long is your price valid, and how will you handle cement and rod price rises?
  • What advance do you need, and what are the payment stages?
  • Who will supervise the site day to day, and how often will you visit?
  • What is your programme, week by week, and when will you finish?
  • What happens to defects after handover?

Ask every bidder the same questions in writing, and compare the answers as carefully as the prices.

Tricks to Watch For

  • Provisional sums: "Allow ₦1,000,000 for electrical" looks like a price but isn't. The real cost comes later.
  • Low quantities: a contractor can show a low total by pricing fewer m² of blockwork or tiling than the building needs. Compare quantities, not just rates.
  • Cheap specification: 6" blocks instead of 9", 0.40 mm roofing instead of 0.55 mm, one coat of paint instead of two.
  • Front-loading: high prices for early work (substructure) and low ones for late work (finishes), so most of the money is paid early.

Frequently Asked Questions

How many quotes should I get?

Three is a good number for a house: enough to compare, few enough to check properly. More than five rarely helps unless you're running a formal tender.

Should I always reject the lowest quote?

No. Reject it only if it's missing work, uses a cheaper spec, or the contractor scores badly on track record and team. If the lowest bidder can explain their price and has finished similar buildings, it may be the best choice.

What if all the quotes are far above my estimate?

Check your estimate's spec and scope match what you sent the contractors. If they do, prices may have moved. Check current material prices. Or the market is busy and contractors are pricing high. Consider building in stages.

Download the Comparison Sheet

Free Tender / Quote Comparison Sheet (Excel + PDF) that works out how far each bid is from your estimate and scores the contractors. Want a second opinion on one quote? Try the Quote Checker.

Check a quote →
🔔

Get building price alerts on this phone

One alert a week when cement, rods or blocks change price, or a new cost guide is out. Free, with no sign-up and no email.

Your own figure

Want an accurate cost for your own project?

Get an itemised estimate priced for your city — free, no account needed.

Calculate your building cost →