Building permit fees are one of the most common budget surprises in Nigerian construction — particularly for first-time builders in Lagos and Abuja who are not prepared for how much the government charges for the right to build on their own land. This guide gives you the 2026 state-by-state breakdown, explains what the fees cover, and tells you what to watch out for in the application process.
Building Permit Fees by State (2026)
| State | Approving Authority | Residential Permit Range | Typical Timeline |
|---|---|---|---|
| Lagos | LASPPPA + LASBCA | ₦500,000–₦1,500,000+ | 4–8 weeks |
| Abuja (FCT) | FCDA DHUD | ₦300,000–₦900,000 | 6–10 weeks |
| Rivers / Port Harcourt | Rivers MUDPP | ₦200,000–₦600,000 | 6–12 weeks |
| Ogun | SUDEMA | ₦100,000–₦350,000 | 4–8 weeks |
| Oyo / Ibadan | OYOWMA | ₦80,000–₦250,000 | 4–8 weeks |
| Enugu | ENSUDA | ₦50,000–₦150,000 | 3–6 weeks |
| Delta | Delta BPPPA | ₦80,000–₦250,000 | 4–8 weeks |
| Anambra | ANAMBRA SMUPA | ₦50,000–₦180,000 | 3–6 weeks |
| Kano | KNUPDA | ₦60,000–₦180,000 | 4–8 weeks |
| Cross River | CRSMUPD | ₦60,000–₦200,000 | 4–8 weeks |
| Other States | State Physical Planning Authority | ₦40,000–₦150,000 | 3–8 weeks |
Note: These figures are for standard residential buildings (bungalow or duplex). Commercial buildings, blocks of flats, and buildings above 3 storeys attract higher fees. All figures are government fees only — consultant handling fees are additional.
Why Is Lagos So Much More Expensive?
Lagos applies the most complex fee structure in Nigeria. The full permit cost in Lagos is not one fee but a combination of several charges payable to different agencies:
- LASPPPA plan approval levy: Calculated on number of rooms and floor area — the primary permit fee
- Infrastructure levy: A per-m² surcharge for infrastructure provision
- Development levy: Based on project type and zone designation
- LASBCA inspection fees: Separate fees paid to LASBCA for each of four mandatory inspections during construction (foundation, lintel level, roofing, completion)
- Regularisation surcharge (if applicable): Additional charge if the project starts before the permit is issued
A 4-bedroom duplex in Lagos can accumulate over ₦1.5 million in total government fees before consultant charges.
What Is the Consultant's Fee Separate from the Government Fee?
Your town planner or architect handles the permit submission. Their fee for managing this process is separate from the government fee paid to the planning authority. These service fees in 2026:
- Lagos: ₦100,000–₦350,000 for residential permit handling
- Abuja: ₦80,000–₦250,000
- Port Harcourt: ₦70,000–₦200,000
- Other states: ₦40,000–₦120,000
Documents Required for a Building Permit (All States)
While each state has specific requirements, the following documents are needed across all states:
- Title document: Certificate of Occupancy (C of O), Deed of Assignment, or Right of Occupancy
- Recent survey plan by a registered land surveyor
- Architectural drawings (site plan, all floor plans, elevations, sections) — stamped by NIA-registered architect
- Structural drawings — stamped by COREN-registered structural engineer
- Soil investigation report (mandatory in Lagos and Abuja for 2+ storeys; recommended everywhere)
- Completed application form (obtained from the planning authority)
- Payment receipts for all applicable fees
The Hidden Costs: What Applicants Often Don't Budget For
Stamp Duty on Application
In some states, the application forms and approval documents attract stamp duty under the Stamp Duties Act. This is typically a small percentage of the assessed fee value but adds to the total.
Drawings Revision Costs
If your drawings are rejected for not meeting setback requirements, density requirements, or technical standards, they must be revised and resubmitted. Architectural revisions typically cost ₦30,000–₦100,000 per revision round.
Delay Costs
In Lagos and Abuja especially, permit approval can take longer than the published timeline if drawings need revision or if the planning authority is backlogged. Contractors who are standing by while the permit is processed may charge a standby cost, and your project timeline is extended.
LASBCA Stage Inspections (Lagos)
Each of the four mandatory LASBCA inspections in Lagos (foundation, superstructure, roofing, completion) attracts a separate inspection fee of ₦15,000–₦80,000 depending on the building size. Budget for all four from the start.
Retroactive Permit (Regularisation)
If you have already started building without a permit, most states offer a regularisation process to retroactively approve the structure. Lagos's regularisation scheme charges a premium above the standard permit fee — typically 50–100% additional. The regularisation application also requires the building to meet current planning standards; if it does not (setback violations, for example), partial demolition may be required before regularisation is approved.
Building Permit vs Development Permit
A building permit (plan approval) gives you permission to build. A development permit (or development consent) is required in some states for changes of use — for example, building a commercial structure in a residential zone. If your building includes mixed use (e.g., ground-floor shop, residential above), you may need both. Your town planner can advise on whether a development permit is additionally required for your specific project in your zone.
Frequently Asked Questions
Can I start building before the permit is issued?
No — this is illegal in all states and is a common trigger for Stop Work Orders and regularisation surcharges. Some people start site clearing and perimeter fence while the permit is being processed, which is generally tolerated. But foundation concrete and any structural work must wait for the approved permit card. In Lagos, even perimeter fencing has its own approval requirement in some zones.
How long is a building permit valid?
Typically 2–3 years in most Nigerian states, with renewable extensions. If your project takes longer than the permit validity period, you may need to apply for an extension. Lagos issued 2-year permits that can be renewed once for a further 2 years.
What if I build something different from the approved drawings?
This is called unauthorised development and is a common issue in Nigeria. The building control authority may issue a stop work order, require you to bring the structure back into compliance with the approved drawings, or impose a fine and charge a variation fee to approve the change formally. Significant structural departures (adding a storey, changing the roof type) typically require a fresh permit application for the revised design.
Do I need a permit to build a boundary fence only?
In Lagos — yes. LASPPPA requires a fence permit separately from the building permit. In most other states, a fence alone does not require a permit, but check with your local planning authority before starting, particularly for fences above 1.8m height.
Budget Permit Fees Alongside All Professional Costs
The Professional Fees Calculator includes your state's building permit range as a separate line item alongside architect, structural engineer, QS and soil test fees. Select your state, enter your construction cost, and see the full professional fee budget — including the permit — in one place. For the complete step-by-step permit process in your state, see the Building Permit Guide.
Calculate All Your Professional Fees in One Place
The free Professional Fees Calculator covers architect, structural engineer, QS, soil test, building permit and town planner fees — all in one screen, adjusted for your state.
Open Professional Fees Calculator →