Building Permit Guide

How to Get a Building Permit in Nigeria

State-by-state guide covering documents required, the approval process, costs and timelines — for Lagos, Abuja, Rivers, Ogun, Oyo, Enugu and Delta.

Never build without a permit. In Lagos, Abuja and increasingly other states, unapproved structures face Stop Work Orders, fines, and demolition — with no compensation. The permit process feels slow, but the risk of building without it is far greater than the delay.

Approving Authority

Lagos State Physical Planning Authority (LASPPPA)

Typical Permit Cost

₦500,000 – ₦1,500,000

Timeline

4 – 8 weeks (straightforward residential)

How the fee is calculated: Calculated as: Building Volume (L × W × H) × Zone Rate + Layout Fees (₦100,000) + Registration Fee (₦50,000) + LPO (10% of building assessment). Island zones cost more than Mainland.

Documents Required

  • Registered Survey Plan (must be on Lagos State database)
  • 5 sets of Architectural Drawings (floor plans, elevations, sections)
  • 5 sets of Structural Drawings (stamped by licensed structural engineer)
  • Soil Test Report (mandatory for buildings above 2 floors)
  • Tax Clearance Certificate (last 3 years)
  • Land Use Charge Receipt
  • Proof of Ownership (C of O, Deed of Assignment, or other title)
  • Completed Application Form (from LASPPPA)
  • Environmental Impact Assessment (for commercial or 4+ storey buildings)

Step-by-Step Process

1

Engage your Architect and Structural Engineer

They prepare the drawings. Confirm your architect is registered with ARCON (Architects Registration Council of Nigeria).

2

Conduct a Soil Test

Now mandatory for buildings above 2 floors and strongly recommended for all. Produces a geotechnical report that informs your foundation design.

3

Verify your Survey Plan is registered

Your survey plan must be searchable on the Lagos State surveying database. Unregistered plans will delay your application.

4

Submit application to LASPPPA

Submit all documents and pay the processing fee at the nearest LASPPPA office. Keep your receipts.

5

Site inspection by LASPPPA officer

An officer visits your site to confirm the proposed building matches your plot and surroundings.

6

Approval and collection

Collect your Development Permit. Post it visibly on your site during construction as required by law.

7

Obtain LASBCA Stage Certifications

LASBCA inspects at key stages (foundation, DPC level, roofing, completion). Do not skip these — they are required for your Completion Certificate.

Practical Tips for Lagos

  • Many people use a Town Planner or permit expediter to navigate the process — budget ₦50,000–₦150,000 for this service.
  • Confirm your land is not on government-acquired or restricted land before applying — a Land Information Certificate from LASPPPA is useful.
  • Island zones (Lagos Island, Victoria Island, Ikoyi, Lekki) have higher zone rates and stricter setback requirements.
Enforcement: Stop Work Order, fines, and potential demolition for unapproved buildings — LASBCA actively inspects in Lagos.

Frequently Asked Questions

Can I start building before the permit is issued?

No. Commencing construction before your permit is issued is illegal in all states. You can prepare the site (clearing, setting out) but no concrete or blockwork before approval is in hand.

What happens if I build without a permit?

In Lagos and Abuja especially, unapproved buildings face demolition — sometimes with very short notice. You may also face fines and be unable to sell or mortgage the property later since title cannot easily be perfected on an unapproved structure.

Do I need a permit for a fence?

Yes in most states. Fencing above a certain height (typically 1.8m) requires approval. In Lagos, fencing fees are included in the standard permit application.

How long does the permit last?

Most state building permits are valid for 2–3 years. If construction is not completed within the permit period, you typically need to apply for an extension or renewal.

What is the difference between a building permit and a C of O?

A building permit is the approval to construct a specific building on your land. A Certificate of Occupancy (C of O) is a land title document showing you have the right to occupy and use the land. They are separate — you can have one without the other, though you ideally need both.

Calculate your total professional fees including the permit

Use the free Professional Fees Calculator to get a full breakdown of architect fees, QS fees, soil test and permit costs for your project.