Nobody plans a house around the cost of electricity on site, but somebody has to pay for it. Fuel for welding, drilling and pumping water, plus lights for the security man at night, can add up to hundreds of thousands of naira on a small house and millions on a larger building. With diesel above ₦1,800 a litre, it deserves its own line in the budget.
Planning to install solar?
Size a system for your appliances, then ask for quotes from an installer in your area. It is free to ask.
Size it and request quotes →This guide shows what each option costs, using fuel prices from late 2026, and helps you decide what your site actually needs. The figures are worked examples, so replace them with your own quotes.
What Actually Needs Electricity on a Site?
On many house sites, the concrete mixer and poker vibrator run on their own petrol or diesel engines, so they do not need a generator at all. Electricity is usually needed for smaller jobs. Typical loads are shown below, but the figure on your own machine's rating plate is the one to use.
| Equipment | Typical power | Notes |
|---|---|---|
| LED security light | 30–50 W each | Runs all night |
| Phone charging | Under 50 W | Small, but people will expect it |
| Electric drill | 500–1,000 W | Used in short bursts |
| Angle grinder | 900–2,400 W | Cutting rods and tiles |
| Water pump (1 HP) | About 750 W running | Can draw about three times more when starting |
| Welding machine (200 A inverter) | About 5,000–8,000 W | Gates, burglary proofs, steel roofs |
The important point is that a typical bungalow site and a large block of flats need very different things. The first needs a few hours of light power each day. The second may need a large generator running most of the working day.
What Generator Power Costs per Hour
A generator's fuel use depends on how hard it is working. The figures below come from a widely used approximate chart for a 20 kW diesel generator, converted to litres (Hart fuel chart). Note that 20 kW is about 25 kVA, and that a real machine may differ. We have priced diesel at ₦1,900 a litre delivered to site. Dangote's gantry price was ₦1,840 from 28 October, and retail and delivery add to that (Legit.ng).
| Load on a 20 kW set | Litres per hour | Fuel cost per hour | Cost per kWh |
|---|---|---|---|
| ¼ load (5 kW) | 2.3 | ₦4,370 | ₦874 |
| ½ load (10 kW) | 3.4 | ₦6,460 | ₦646 |
| ¾ load (15 kW) | 4.9 | ₦9,310 | ₦621 |
| Full load (20 kW) | 6.1 | ₦11,590 | ₦580 |
Look at the last column. A generator running at a quarter of its capacity costs about 50% more for each unit of electricity than one working at full capacity. Buying a generator that is too big for your site wastes money every hour it runs. Diesel engines can also be damaged by running at very light loads for long periods.
That table counts fuel only. Oil, filters, servicing, a person to look after it, and repairs all come on top.
Small petrol generators
For a house site, a small petrol generator is the usual choice. Fuel use varies by model and load, so as a working assumption we use about 1 litre an hour for a 2.5–3.5 kVA set under moderate load. With petrol at about ₦1,360 a litre, that is about ₦1,360 an hour. If that machine delivers about 1.5 kW, each unit of electricity costs about ₦900.
You can measure your own figure in an afternoon. Fill the tank to the brim, run the generator on normal site work for a set number of hours, then measure how much it takes to fill it up again. Divide the litres by the hours.
How Grid Electricity Compares
If there is a supply near your plot, grid power is far cheaper per unit. Band A customers, who are meant to get at least 20 hours a day, generally pay around ₦209.50 per kWh before 7.5% VAT, or about ₦225 with VAT (BillsGuide). Published rates vary a little between distribution companies, so check your own.
| Source | Approximate fuel or energy cost per kWh |
|---|---|
| Grid, Band A, with VAT | ₦225 |
| Diesel, 20 kW set at full load | ₦580 |
| Diesel, 20 kW set at half load | ₦646 |
| Small petrol set (our assumption) | ₦900 |
So diesel generation costs about two and a half to three times as much as Band A power, and a small petrol set about four times as much. There are three catches, though:
- Getting connected costs money and takes time. You may need a meter, poles or cable, and approval from the distribution company. We could not find a published price for a temporary site connection, so ask your DisCo in writing. Our Mobilisation Calculator includes a utility connection line that starts at ₦300,000 for larger projects. That is only a placeholder for you to replace.
- Supply may be limited. Most feeders are not Band A. You may still need a generator when the power is off.
- The tariff class may be different. A site may not be treated like a home. Ask which class you will be billed under.
Where the supply is reliable and the job will last many months, the connection usually pays for itself, and the meter can stay in use after you move in. For a short job, it may not be worth the trouble.
Which Generator Size Do You Need?
- List what will run at the same time, not everything you own.
- Add the running power in watts, and then allow for the starting surge of the largest motor.
- Convert to kVA. Divide kW by a power factor of about 0.8. So 4 kW is about 5 kVA.
- Add a margin of about 20%, but no more than you need.
Welding drives the decision. A 200 A welder may not run properly on a small 2.5 kVA set. Many builders simply hire a welder who brings a suitable generator for the days the steelwork is being done, which is often cheaper than buying a bigger machine for the whole job.
Buy or Hire?
Prices vary widely by brand, and listings are not always up to date. These are the ranges we found:
| Size | Price seen online | Source |
|---|---|---|
| 2.5–3.5 kVA, budget brands | About ₦60,000–₦175,000 | Nigerian Queries, NaijaTechGuide |
| 2.5–3.5 kVA, premium brands | About ₦280,000–₦725,000 | NaijaTechGuide |
| 20 kVA diesel | About ₦3.35 million–₦8.95 million | NaijaTechGuide |
| 20 kVA Perkins, one dealer | ₦5.8 million | Titanium Power Solutions |
The NaijaTechGuide list was last updated in January 2026, and another guide puts the same Perkins 20 kVA at ₦2.3 million to ₦3.95 million, so the gap between sources is large. Treat these as a guide and get current quotes.
Published hire rates for small generators are hard to find, so ask at least three companies. Find out whether the price is "wet" (fuel included) or "dry" (you buy the fuel), who pays for delivery, and who repairs it if it breaks down.
A simple rule: for a house, buying a small petrol generator usually makes sense, because you will keep using it or can sell it after the job. For a big generator needed for only a few weeks, hiring is usually better. To decide, multiply the hire rate by the number of days you need it and compare that with the purchase price, less what you could resell it for.
Where Solar Makes Sense on Site
Solar is not the answer for welding or heavy tools on most sites, but it suits one job very well: night lighting and phone charging. A security light running on a generator is one of the most wasteful ways to use fuel, because the engine is mostly idling.
Here is a small kit, priced from the indicative rates in our own library:
| Item | Indicative cost |
|---|---|
| 1 kVA inverter | ₦180,000 |
| 200Ah, 12V battery | ₦150,000 |
| 400 W of solar panels, installed | ₦140,000 |
| Total | about ₦470,000 |
This setup could run about 100 W of LED lights for 12 hours a night, or about 1.2 kWh, which is close to the limit of what the battery and panels can sustain. Compare that with running a petrol generator all night. At about 1 litre an hour, 12 hours costs about ₦16,300 in fuel. Even if the generator used half that amount, the kit would pay for itself in about two months. Afterwards, you can move it into the finished house as a starting point for backup power. Get a current quote, as solar prices move with the exchange rate. Use the Solar Calculator to size a larger system, and see our comparison of solar and generators for the finished home.
Two Worked Examples
A three-bedroom bungalow over six months
Assume a small petrol generator runs for 3 hours a day, 24 days a month, for six months. That is 432 hours.
- Petrol: 432 hours × 1 litre × ₦1,360 = about ₦590,000
- Generator: about ₦150,000 to ₦450,000, depending on the brand
- Total: about ₦740,000 to ₦1.04 million, before servicing
- The same energy from Band A grid power at 1.5 kW: 648 kWh × ₦225 = about ₦146,000, plus the cost of getting connected
A block of flats using a 20 kW diesel generator
Assume it works at half load for 8 hours a day, 24 days a month.
- 8 hours × 3.4 litres × ₦1,900 = about ₦51,700 a day
- Over 24 days: about ₦1.24 million a month in diesel alone
On a job like this, a ₦100 change in the price of diesel adds about ₦65,000 a month, which is why fuel price clauses matter on longer contracts.
How to Keep Site Power Costs Down
- Batch the power-hungry work. Do all cutting, drilling and welding on set days, rather than starting the generator for one small job.
- Pump water into tanks in one go, instead of pumping several times a day.
- Control the fuel. Keep it locked up, log every refill, and compare the log with hours run. Fuel theft is common.
- Agree who pays for fuel in writing. Your contract should state whether the contractor or the owner buys it. Our Quote Checker can help you spot whether it has been priced.
- Service it on schedule. A generator with a dirty air filter or old oil burns more fuel.
Safety
Generator fumes contain carbon monoxide, which can kill without warning. Never run a generator indoors or in an enclosed part of the building, and keep it well away from doors, windows and where workers or the security man sleep. Store fuel away from the generator in proper containers, and let the engine cool before refuelling. Earth the generator correctly, keep cables off wet ground and away from traffic, and use a qualified electrician for any connection to the building's wiring.
Frequently Asked Questions
How much diesel does a generator use per hour?
An approximate chart puts a 20 kW set at about 2.3 litres an hour at quarter load, 3.4 at half load, 4.9 at three-quarter load and 6.1 at full load. Actual consumption depends on the machine and its condition, so measure yours.
What size generator do I need to build a house?
For lights, drills, grinders and a small pump, a 2.5–3.5 kVA set is often enough if you do not run everything at once. Welding usually needs more, so many builders use a welder who brings a suitable generator.
Is it cheaper to run a generator or use NEPA on site?
Per unit, grid electricity is much cheaper: about ₦225 per kWh on Band A with VAT, compared with roughly ₦580 to ₦900 from fuel. But you must also pay for the connection, and supply may be limited on lower bands.
Where does site power go in my budget?
It usually goes under preliminaries. Add it in the Preliminaries Calculator, and read what mobilisation covers so you can check it is not left out or counted twice.
Can I use solar instead of a generator on site?
For night lights and phone charging, yes. For welding and heavy tools, a generator or grid supply is usually more practical unless the solar system is large.
Put Site Power in Your Budget
Site power is easy to forget and expensive to discover later. Add it with the Preliminaries Calculator and Mobilisation Calculator, then get your full building cost in the free Estimator.